HEP launches tender to build Kosinj hydropower plant in Croatia

Croatia’s national power company Hrvatska Elektroprivreda (HEP) invites prequalification bids by 1 March 2027 from qualified contractors for the construction of the main civil works and the supply of equipment for the Kosinj hydropower plant in Lika-Senj County.

The tender covers main civil engineering structures, electromechanical equipment, and grid connections, while excluding preparatory replacement roads and water-diversion tunnels, which have already been tendered separately.

The scope of contract will comprise:

  1. Construction of the Kosinj dam (58.5 m high), Bakovac dam (47.9 m high), and Sedlo dam (24 m high), to impound the Kosinj reservoir, an 11.45 km² storage basin holding roughly 340 x 106 m3 of water, and including extensive geological sealing (injection curtains) to prevent karst water loss;
  2. Construction of the Kosinj powerhouse, rated at roughly 34.6 MW, equipped with two generating units (22 MW and 12.6 MW);
  3. Modernisation of the existing Sklope plant, including replacing its 22.5 MW turbine with a 24.7 MW unit, and,
  4. Construction of a 110 kV switchyard, overhead transmission lines, and local distribution network connections.

The construction of Kosinj represents part of the expansion of the 238.5 MW Lika-Gacka hydro system, built in the 1960s, which currently comprises the Sklope (22.5 MW) and Senj (216 MW) plants. The project will entail the construction of the Kosinj and 375 MW Senj 2 hydropower plants, to utilize the remaining hydro potential of the Lika and Gacka watershed, as well as regulating floods in the river basin in the Kosinj valley, and optimizing the operation of the existing system.

The addition of 425 MW (320 GWh), primarily of peak energy, will raise total installed capacity in the watershed to 665 MW and average annual production to 1.5 TWh.

HEP obtained the location permit for Kosinj in 2019 and the project was designated a strategic state project by the Government in July 2021. Construction of Kosinj is currently projected to begin in July 2027 and to take more than six years to complete.

The procurement procedure published on the EU’s procurement platform TED and in Croatia’s Electronic Public Procurement Gazette, is a two-stage negotiated procedure. Interested contractors must first apply for pre-qualification before selected bidders are invited to submit formal technical and financial offers.

Procurement documents can be accessed and bids in Croatian submitted via https://eojn.hr/tender-eo/100930. For further information, contact: Procurement department, HEP d.d., Ulica grada Vukovara 37, Grad Zagreb 10000, Croatia; Email: info_nabava@hep.hr; Tel.: +385 16322111; www.hep.hr.